FLG-ORIF-4IN
Orifice Flange Pair 4in 300# CS
Shortage Quantity
6
Need by May 1, 2026
— supplier lead time is 28 days (Continental Flange & Fitting).
Standard ordering window has passed. Expediting required.
Total Demand
6
On Hand
0
On Order
0
Net Short
6
Days Until Needed
22